May 23, 2011
Hodges
Farm & Bullard Road
Contract
I
want to update you on the Hodges
Farm Road and Bullard Road contract with Key
Paving. Here are a few facts:
Background:
- An
invitation
to bid was advertised in the local paper on 8/12/10
Invitation
to
bid
- The
bids were
to be opened on 9/16/10 at 10:00AM by the Public Works director and
possibly others
- The
commissioners met on October 7, 2010 and accepted the bids for Hodges Farm Rd.,
Bullard Rd.
and Feldspar Rd.
based
on the Public Works director’s recommendation
Oct.
7, 2010 meeting minutes
On
4/26/11, I requested a copy of the Hodges Farm Rd. contract after
finding out we did not
have a contract on Feldspar
Rd.
I made several more requests for this contract, and still did not have
it by
the meeting Monday night (5/16/11).
Responses
by Greg Wood, County
Manager,
via emails:
1. Will Brown was busy
and did not have time to
get a copy of the contract
2. Lakeysha
Wright’s father had died and she was
out of the office so she could not get a copy
3. Betty Moon must have
lost it so they had to
get a copy from Key Paving
On
5/17/11 I went to
the courthouse and finally received a copy as
I had sent an email demanding a copy the
evening of 5/16/11 after the meeting.
This is the county's copy and
"all we have in the file." This was supposedly obtained from
Key Paving per email from County
Manager,
Greg Wood.
In my
opinion, several issues
call the legality of the Contract into question:
CONTRACT:
- The contract has NO scope of work. It
does not describe what will be done, when, or how
- There are no appendices or detail
specifications of the contract
- The contract says that for the sum of
$192151.05 contractor will provide all materials, etc. while
the in fact the county is providing the materials.
- The contract does not address the warranty
provided to the County by the contractor.
- The county attorney did not sign the
contract.
- The contract is only 2 pages long with page
2 being the signature page.
- It appears the signature lines have been
whited out and the County
Manager
and Chairman have signed on the whited out areas. The
same is true for the signature of Key Paving official.
- The type is completely different where the
Chair’s name and title have been typed. The
same is true where Ricky Adams has signed for Key.
Is he the Corp Sec or President or Vice
President? All type is different.
PERFORMANCE BOND:
- There is a performance bond that does not
list what work the bond is for-no scope of work.
- There is no surety listed, and there is no
letter from the surety nor is there a bond number given.
The surety did not sign the performance bond. (It is therefore worthless.)
- There is no power of attorney attached to
validate the person that is signing for the surety company.
- No date is entered for the contract date.
- Bond is not issued by a Surety Company
LABOR AND MATERIAL PAYMENT BOND:
14. Cecil Key Paving, Inc. is listed as the
Surety!
15. Cecil Key Paving, Inc. is listed in the
space for the
amount of the bond.
- No where on the bond does it list or refer
to the surety company issuing the bond and is not signed by the surety
company.
- There is no letter from the surety nor is
there a bond number given. The surety did
not sign the performance bond. (It is
therefore worthless.)
- Bond is not issued by a Surety Company.
The
irregularities with the bonds means they are not valid and the county
has no
recourse on workmanship or completion of the jobs contracted
OTHER IRREGULARITIES:
- The contract was purportedly signed
September 21, 2010 by the County Manager,
Greg Wood, and the BOC Chair, Charles Hill, as well as the contractor.
- Greg Wood signed as County Clerk,
when in fact he was not
County
Clerk until 2011.
- All bonds are also dated September 21, 2010.
- The Board of Commissioners did not get the
bids or approve them until October 7, 2010.
- The type is different throughout the
contract where things have been changed.
I
emphasize the date to you because somehow this contract was signed 17
days before the BOC saw the bids and approved them at their October 7,
2010 meeting.
OTHER
QUESTIONS THAT NEED ANSWERS:
·
Why did Key
Paving get the “go ahead” to do work on Jackson Lake Rd.
and Harvey Lane Rd.
without a bid? (Over $300,000 of work)
·
Why were no bids obtained
and only quotes gotten and who was responsible for this?
·
Why wasn’t STATE
procurement law (OCGA 36-91-20, 21, 22) followed? And
why wasn’t the attorney allowed to answer
this question before a vote was taken?
·
Is Key Paving
being allowed to make up losses on Hodges Farm Rd. and Bullard Rd.
by being allowed to do
$300,000 of work on other roads without bids? Is
this the only way we can get Key Paving to
come back and finish
the work since there is actually no contract and no bond?
·
Why do the County Manager,
Greg Wood, and Public Works Director, Will Brown, continue to tell the
BOC
there are contracts when in fact there are not and never have been?
·
Why has Will
Brown repeatedly come to the BOC for more money for this contractor,
even
though the work is not done and the part that was done was not done
correctly?
·
When was the
“contract” with Key Paving actually signed and why would it
be signed without
any protections for the county and no scope of work listed?
·
Who originally
signed this contract because it appears the signatures had to be
whited out and re-signed?
In my
opinion the
handling of this contract by county staff constitutes gross negligence
and very possibly
fraud.
POSSIBLE SOLUTIONS:
1.
There must be more checks and balances,
including
allowing the full board and the county attorney to sign any
contract over $50,000.
2.
Any other contract must be signed by at
least two
board members and the county attorney.
3.
The County Manager
and the Public
Works Director shall have NO authority to sign any contract, nor should
any
other employee of the county. (Add to
County Personnel Policy by resolution)
4.
ALL work over $50,000 performed for Jasper County
should require properly executed Payment and Performance Bonds in favor
of Jasper
County.
5.
All contracts must be accompanied by a
complete,
specific “scope of work” detailing exactly what is to be
done and the cost of
the work.
6.
Any commissioner signing a contract without
formal
board approval shall be reprimanded by the Board and pay a fine of $500.
7.
Any employee signing a contract (prohibited
in #3) or
entering into any agreement with a vendor without formal board approval
shall
be terminated. (Add to County Personnel
Policy by resolution)
SUGGESTED REPRIMANDS:
The County Manager
and the Public Works director shall both be reprimanded for:
1.
making false
statements to the Board by telling them there was a contract on these
roads as
well as Feldspar Rd.
2.
putting the county
in a costly and risky financial situation by not having performance and
payment
bonds
The County
Manager
shall also be reprimanded for:
3.
covering up the
fact that there was not a contract by signing an invalid contract
4.
instead of
disciplining the Public Works director
for negligence the County
Manager
has made excuses
for him
Formal
reprimands shall be placed in each employee’s
respective personnel file and made a
part of the minutes of the Board of Commissioners.
|